Z--IA-PORT LOUISA NWR-BOAT RAMP REPAIR PROJ
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The US Fish and Wildlife Service (FWS), specifically the FWS, CONSTRUCTION A/E TEAM 2 office, is soliciting quotes for the repair and replacement of a damaged public boat ramp at the Port Louisa National Wildlife Refuge (NWR) in Wapello, IA. This project involves removing the existing concrete ramp and replacing it with a new, larger concrete ramp to address degradation and safety hazards. This is a Total Small Business Set-Aside. Quotes are due by March 27, 2026.
Scope of Work
The project entails the removal of the existing concrete boat ramp and its replacement with a new concrete boat ramp. The new ramp dimensions will be 12' x 28' x 6". Key tasks include:
- Demolition and removal of the existing damaged concrete and rebar.
- Preparation of the bedding for the new concrete section using a backhoe/excavator.
- Fabrication of formwork and installation of new rebar.
- Pouring new high-strength concrete (4,000 psi or greater) with imbedded traction bars.
- All necessary materials, equipment, and labor are to be provided by the contractor. The work aims to address concrete degradation and exposed rebar, ensuring continued safe use of the ramp.
Contract & Timeline
- Contract Type: Solicitation for Repair or Alteration of Other Non Building Facilities (Z2PZ).
- Set-Aside: Total Small Business Set-Aside (FAR 19.5).
- Period of Performance: April 27, 2026, to October 2, 2026. Work is to be coordinated with Contractor and Refuge Staff, with an ideal period between July 15, 2026, and October 2, 2026, based on optimal river conditions (low river depth).
- Location: Port Louisa NWR, 10295 120th Street, Wapello, IA 52653.
Submission & Evaluation
- Site Visit: A site visit was held on March 11, 2026, at 9:00 AM CST.
- Questions Due: Questions were due by March 12, 2026, to Bill Koski (william_koski@fws.gov).
- Quotes Due: March 27, 2026, at 3:00 PM EST. Quotes must be emailed to Bill Koski (william_koski@fws.gov).
- Offers must be submitted within 10 calendar days of award and completed within 91 calendar days after receiving notice to proceed. Offers providing less than 10 calendar days for Government acceptance after the due date will be rejected.
- Bidders must acknowledge receipt of Amendment 0001.
Additional Notes
- No performance or payment bonds are required.
- Contractor responsibilities include notifying refuge staff at least one week prior to starting work, completing work as soon as feasible to avoid river level fluctuations, cleaning equipment pre and post entry to prevent invasive species spread, and minimizing disturbances to refuge facilities.
- Equipment and materials left on-site must be secured by the contractor in a designated gated area.
- Mississippi River levels may cause construction delays, potentially requiring an extension to the period of performance.
- The solicitation number is 140FC226Q0014.