Repair Base Switching Station

SOL #: FA489726B0006Combined Synopsis/Solicitation

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Air Force
FA4897 366 CONS PKP
MOUNTAIN HOME AFB, ID, 83648-5296, United States

Place of Performance

Mountain Home AFB, ID

NAICS

Power and Communication Line and Related Structures Construction (237130)

PSC

Repair Or Alteration Of Epg Facilities Other, Including Transmission (Z2MZ)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Apr 14, 2026
2
Submission Deadline
May 21, 2026, 10:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of the Air Force, specifically FA4897 366 CONS PKP, is soliciting proposals for the Repair Base Switching Station project at Mountain Home Air Force Base, ID. This critical project involves constructing a new electrical switching station (Building B1017), transitioning base electrical loads from the existing station (Building 1406), and subsequently demolishing the old facility. The acquisition is a Total Small Business Set-Aside and will follow a Two-Step Sealed Bidding process for a Firm-Fixed-Price contract, estimated between $10,000,000 and $25,000,000. Technical proposals are due May 21, 2026, at 4:00 PM MDT.

Scope of Work

  • Construction: Build a new, complete, and operational electrical switching station (B1017) to current industry standards, including site work, foundations, structural steel, installation of medium-voltage electrical equipment (12.47kV), control building construction, power ductbanks/conduits, and final commissioning.
  • Transition: Seamlessly transfer all base electrical loads from the old switching station (Bldg 1406) to the new Bldg 1017.
  • Demolition: Demolish the existing switching station (Bldg 1406), including necessary PCB sampling and analysis for remediation waste.
  • Special Requirements: Careful excavation to avoid existing underground utilities, adherence to stringent standards, integration of SCADA communications, and a Mass Notification System. The project also requires Power Flow, Short Circuit, Arc Flash, Coordination, and Reliability studies.

Contract Details

  • Contract Type: Firm-Fixed-Price.
  • Magnitude: Estimated between $10,000,000 and $25,000,000.
  • Project Duration: 850 calendar days total from Notice to Proceed, comprising 120 days for pre-construction and 730 days for construction activities.
  • Set-Aside: Total Small Business Set-Aside (FAR 19.5), with a Small Business Size Standard of $45,000,000.
  • Funding: Award is contingent upon the availability of funds.

Submission & Evaluation

  • Process: Two-Step Sealed Bidding. Step 1 requires submission of unpriced technical proposals for acceptability evaluation. Step 2 invites offerors with acceptable technical proposals to submit sealed price bids, with award going to the lowest responsive, responsible bidder.
  • Technical Proposals Due: May 21, 2026, 4:00 PM MDT.
  • Questions/RFIs Due: May 8, 2026, 4:00 PM MDT.
  • Evaluation Factors: Technical Approach & Understanding, Transitioning Plan, Commissioning Plan, Excavation Plan, Traffic Flow & Parking Management, Relevant Experience, Key Personnel Qualifications, Safety Program, Quality Control/Assurance & Project Management Plan, and Environmental Plan.
  • Submission Method: Technical proposals must be submitted via email to the listed CONS POCs.

Important Notes

  • Site Visit: A site visit is scheduled for April 29, 2026, at 10:00 MDT. Attendees must submit specific information to the CONS POCs by April 27, 2026, 4:00 PM MDT.
  • Base Access: Personnel requiring access to Mountain Home AFB must comply with REAL ID Act requirements (effective May 7, 2025) and follow base access procedures, including submitting a 366 SFS FORM 30 two weeks prior.
  • Attachments: The solicitation includes 14 attachments, such as the Statement of Work, Design Drawings, Design Analysis, Specifications, and a comprehensive list of FAR/DFARS Provisions and Clauses.

People

Points of Contact

Ryan RubensteinPRIMARY
Taylor InmanSECONDARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 1Viewing
Combined Synopsis/Solicitation
Posted: Apr 14, 2026
Repair Base Switching Station | GovScope