Timeline

1
Posted
Jan 13, 2026
2
Last Updated
Mar 13, 2026
3
Submission Deadline
Mar 13, 2026, 11:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of the Interior, National Park Service has issued a Solicitation for the Rehabilitation of the Hurricane Ridge Water System at Olympic National Park, Washington. This project involves comprehensive upgrades to the park's public water system. This is a Total Small Business Set-Aside. Proposals are due March 13, 2026, by 16:00 local time.

Scope of Work

The project requires the rehabilitation of the existing Group A public water storage and distribution system. Key tasks include:

  • Replacement of tank fill and distribution system piping, specifically using DR11 HDPE pipe.
  • Demolition and disposal of obsolete above-ground and below-ground infrastructure.
  • Rehabilitation of the 100,000-gallon dual-chamber cast-in-place reinforced concrete water storage reservoir.
  • Installation of a new well pump control panel and associated components.
  • Provision for remote monitoring capabilities for key water system parameters.
  • New work items include the installation of a dry-barrel fire hydrant assembly with associated components and an underground conduit extension for future electrical service.
  • Compliance with federal, state, and local regulations, including environmental protection, safety, and waste management, is mandatory.
  • Trenchless methods are explicitly not acceptable due to archaeological sensitivity.

Contract & Timeline

  • Contract Type: Firm-Fixed Price
  • Period of Performance: April 1, 2026, to October 18, 2026.
  • Set-Aside: Total Small Business Set-Aside (FAR 19.5)
  • NAICS Code: 237110 (Water and Sewer Line and Related Structures Construction), Size Standard: $39.5M.
  • Proposal Due: March 13, 2026, by 16:00 local time.
  • Published: March 13, 2026.

Submission & Evaluation

Proposals must be submitted electronically in separate Volumes (I and II) to michael_davidson@nps.gov or michael_davidson@ios.doi.gov. Each email attachment must not exceed 30 MB. Offerors must be registered in SAM. Evaluation will follow a Best Value Continuum Tradeoff Process, where Technical Capability, Past Performance, and Price are equally weighted and approximately equal to Price.

  • Technical Capability factors include the quality of the impact minimization plan, critical path construction schedule, and relevant prior experience.
  • Past Performance factors include quality, timeliness, business relations, and cost control. CPARS evaluations are acceptable in lieu of Past Performance Questionnaires (Attachment 8).
  • Bidders must incorporate costs for new work items into CLIN 001. A Limitations on Subcontracting Worksheet (Attachment 10) is required, demonstrating compliance with the 85% threshold for general construction. The applicable Davis-Bacon Wage Determination is WA20260022 for Clallam County, Washington.

Additional Notes

No site visit will be held. The Government intends to award without discussions but reserves the right to hold them if necessary.

People

Points of Contact

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 4Viewing
Solicitation
Posted: Mar 13, 2026
Version 3
Solicitation
Posted: Mar 4, 2026
View
Version 2
Solicitation
Posted: Feb 11, 2026
View
Version 1
Pre-Solicitation
Posted: Jan 13, 2026
View
Z--Olympic National Park REHAB HURRICANE RIDGE WATER | GovScope