Z1DA--658-24-106 Replace Bldg 16 HVAC
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of Veterans Affairs (VA) issued this solicitation to replace the HVAC system in Building 16 at the Salem VA Medical Center in Salem, VA. This project was designated as a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside. As of the latest amendment (0005), the public bid opening has concluded, and a bid abstract has been published.
Scope of Work
The contractor is responsible for providing all labor, materials, and equipment to:
- Demolish and replace the existing HVAC air handler, ductwork, and VAV boxes.
- Renovate approximately 2,500 sq ft on the top floor of Building 16.
- Remove and replace the existing ceiling grid and tiles (Armstrong Prelude/Dune systems).
- Modify the fire suppression system to accommodate new ceiling heights.
- Integrate new controls with the existing heating system.
- Perform work under ICRA Level II requirements.
Contract & Timeline
- Type: Firm-Fixed-Price (Sealed Bid/IFB)
- Estimated Value: $500,000 – $1,000,000
- Duration: 270 calendar days from Notice to Proceed (NTP)
- Set-Aside: 100% SDVOSB
- Bid Opening Date: January 20, 2026
Bid Results (Amendment 0005)
A public bid opening was held on January 20, 2026. Seven offers were received:
- BHPE: $249,000.00
- Phillips C&C: $992,372.00
- ASC: $1,100,000.00
- MC3 Solutions: $1,136,794.00
- Tripact LLC: $1,183,000.00
- Jetts Specialty: $1,277,000.00
- HICAPS: $1,475,000.00
Additional Notes
The project requires the prime contractor to perform at least 25% of the construction work with their own labor force. Submittal Exchange is required for project management and documentation.