Z1DA--Install ID Concrete Pad Project 593-26-104 VAMC Las Vegas, NV

SOL #: 36C26126R0054Solicitation

Overview

Buyer

Veterans Affairs
Veterans Affairs, Department Of
261-NETWORK CONTRACT OFFICE 21 (36C261)
MATHER, CA, 95655, United States

Place of Performance

North Las Vegas, NV

NAICS

Commercial and Institutional Building Construction (236220)

PSC

Maintenance Of Hospitals And Infirmaries (Z1DA)

Set Aside

Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14) (SDVOSBC)

Timeline

1
Posted
May 1, 2026
2
Last Updated
Jun 9, 2026
3
Submission Deadline
Jun 29, 2026, 9:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of Veterans Affairs (VA), specifically the VA Southern Nevada Healthcare System (VASNHS), is soliciting proposals for the installation of an Interior Design (ID) Concrete Pad (Project 593-26-104) at its North Las Vegas, NV campus. This project involves constructing a large concrete slab to support two conditioned storage units, including all necessary utilities and grounding. This is a Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside. Proposals are due June 29, 2026, by 14:00 PDT.

Scope of Work

The project requires the installation of a 90' x 61' 4" concrete slab (4" thick) designed to support two 30' x 40' (1200 SF each) storage units. The scope includes:

  • Subgrade preparation (12" thick Class 2 Aggregate Base compacted to 95%).
  • Installation of reinforcing steel and dowels.
  • Underground electrical trenching, conduit (2" RGC above ground, PVC Schedule 40 underground), and pull wire.
  • Provision of two 125 Amp breakers at the existing electrical source and a Christy box.
  • Installation of a UFER ground and an 8' copper ground rod.
  • Construction of an aluminum screen wall fence with gates, including specified hardware and locksets.
  • The storage units will be conditioned tuff sheds (or similar) with underground electrical connections, personnel single doors, and aluminum roll-up doors.
  • Contractor must verify existing site conditions and square footages.

Contract Details

  • Contract Type: Firm-Fixed-Price Construction Contract.
  • Period of Performance: 180 calendar days after Notice to Proceed (NTP).
  • Place of Performance: Storage Yard, VA Southern Nevada Healthcare System (VASNHS), 6900 N Pecos Rd, North Las Vegas, NV 89086.
  • NAICS Code: 236220 (Commercial and Institutional Building Construction) with a $45M size standard.
  • Product Service Code (PSC): Z1DA (Maintenance Of Hospitals And Infirmaries).
  • Wage Determination: NV20260038 05-18-2026 applies.

Submission & Evaluation

  • Proposal Submission Deadline: June 29, 2026, by 14:00 PDT.
  • Submission Method: Electronic copy via email to christopher.whipple@va.gov.
  • Questions Due (RFIs): June 16, 2026, by 14:00 PST, using the provided RFI form.
  • Evaluation Criteria: Lowest priced proposal that is responsive to the RFP. The Government intends to award without discussions but reserves the right to conduct them.
  • Offer Guarantee: A bid bond is required with the proposal.
  • Performance & Payment Bonds: Required within ten (10) days of award.
  • Pre-Proposal Site Visit: Scheduled for June 09, 2026, at 09:00 PDT. Meet at Administration Building #6, police counter/waiting area.

Eligibility & Special Requirements

  • Set-Aside: Total set-aside for eligible Service-Disabled Veteran Owned Small Business (SDVOSB) concerns. Offerors must be registered and certified on SAM.gov and the SBA Small Business Search website prior to evaluation and award.
  • Security Requirements: No access to VA personnel/patient PHI/PII or sensitive information. Contractor IT devices cannot connect to VA internal networks. Adherence to HIPAA is required.
  • Submittals: Project-specific plans (Construction Safety, Environmental Protection, Fire Safety, Quality Control, Waste Management) and other submittals per Specification Section 01 33 23 are due within ten (10) Federal workdays after NTP.
  • Quality Control: A QA/QC plan demonstrating review through a minimum of three phases of inspection/control procedures is required.

Key Documents

Bidders should review the Statement of Work (SOW), Specifications, Drawings, Price Breakdown template, VAAR Clause 852.219-75 (Limitations on Subcontracting), RFI Form, Wage Determination, and Pre-Solicitation Site Visit Presentation.

People

Points of Contact

Christopher WhippleContracting OfficerPRIMARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 5
Solicitation
Posted: Jun 9, 2026
View
Version 4Viewing
Solicitation
Posted: Jun 1, 2026
Version 3
Solicitation
Posted: May 28, 2026
View
Version 2
Pre-Solicitation
Posted: May 12, 2026
View
Version 1
Sources Sought
Posted: May 1, 2026
View