Z2DA--519-23-908 EHRM Tier 2 Data Center Construction - Big Spring
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of Veterans Affairs (VA) is soliciting proposals for the EHRM Tier 2 Data Center Construction project at the West Texas VA Health Care System in Big Spring, TX. This 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside opportunity involves renovating existing space into a new data center. Proposals are due by February 5, 2026, at 12:00 PM ET.
Scope of Work
This project requires a General Contractor to provide all necessary tools, labor, materials, equipment, permits, licenses, supervision, and quality control to construct a new EHRM Tier 2 Data Center. The scope includes demolition of old office, data, bathrooms, and storage space, followed by new construction in Building 1. Detailed specifications cover architectural, mechanical, plumbing, electrical, telecommunications, and fire suppression systems. Key requirements include adherence to VHA Infection Control Risk Assessment (ICRA) and Pre-Construction Risk Assessment (PCRA) protocols, including soundproof panels. Bidders must account for identified asbestos-containing materials (ACM) and lead-based paint (LBP) in Building 1, as detailed in survey and management plans. The project mandates the use of specific brand-name items for compatibility: Motorola Avigilon for security cameras, HID for physical security access control, and Siemens Desigo for the fire alarm system.
Contract Details
This is a Firm-Fixed-Price contract with an estimated magnitude of $5,000,000 to $10,000,000. The performance period is 225 calendar days from the Notice to Proceed (NTP). Contractors must comply with Buy American requirements, prevailing wage rates (Howard County, TX), and supplemental insurance. A Bid Guarantee (SF 24) of not less than 20% of the bid price (not exceeding $3,000,000) is required, with Payment and Performance Bonds (SF 25A and SF 25) due upon award. The solicitation includes limitations on subcontracting, requiring that for general construction, no more than 85% of the amount paid by the government can go to non-SDVOSB/VOSB firms (excluding material costs).
Submission & Evaluation
Offers are due by February 5, 2026, at 12:00 PM ET. Submissions must be emailed to Devin Russell (devin.russell@va.gov) and copied to Richelle Gray (Richelle.Gray@va.gov). The bid opening will be conducted via teleconference on February 5, 2026, at 12:30 PM ET. Award will be made to the responsible bidder whose offer is most advantageous to the government, considering price. Bids should be based on price only; no write-ups on past projects or Past Performance Questionnaires (PPQs) are required. Offerors must be SBA-certified SDVOSBs and registered in SAM.gov.
Key Documents & Notes
The solicitation includes comprehensive drawings and specifications (Volumes 1 & 2). A pre-bid site visit was held on November 18, 2025. All project communications and documentation will utilize a web-based project management software (e.g., Procore). Technical questions and answers have been provided through amendments, clarifying scope, timelines, and tax exemptions (Texas Sales and Use taxes).