CAR LIFT REPLACEMENTS
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Air Force Sustainment Center PZIMA, Robins AFB, GA, is seeking quotes for Car Lift Replacements under a 100% Total Small Business Set-Aside. This Firm-Fixed Price (FFP) Request for Quote (RFQ) requires the provision and installation of three double-sided automotive vehicle lifts at Robins Air Force Base. Quotes are due by February 24, 2026, at 01:00 PM EST.
Scope of Work
The contractor shall provide all materials, equipment, labor, transportation, shipping, setup, and installation for three (3) double-sided Automotive Vehicle Lifts for the 402d Commodities Maintenance Group (CMXG). These lifts must be capable of holding two F-15 Conformal Fuel Tanks (CFTs, weighing 2,125 lbs each), with each side of a double-sided lift having independent controls and a 5,000 lb capacity (10,000 lb total per double-sided lift). The scope includes:
- Disassembly, removal, and palletization of existing lifts (government provides crates, vendor packs).
- Ensuring only one lift is out of service at any given time.
- Functional testing of new lifts with F-15 CFTs.
- Providing a standard one-year warranty on parts and workmanship.
- Compliance with NIST SP 800-171, requiring a satisfactory score of 110 in the Supplier Performance Risk System (SPRS).
- Contractor personnel must complete EMS Awareness and EnMS training.
Deliverables & Requirements
Key deliverables include:
- Operation/Maintenance Manual (CDRL A001): One paper and one electronic copy, 3 days after all units are installed.
- Contractor's Safety Plan (CDRL A004): Draft due within 10 working days post-award, addressing Appendix C Industrial Safety and Health Requirements.
- Accident/Incident Report (CDRL A005): Telephonic notification within 4 hours, electronic within 3 days for mishaps.
- Status Reports for EMS and EnMS Training (CDRL A002, A003).
- Submission of drawings for proposed new lifts within four (4) weeks after contract award.
- A Program Manager must be provided within five (5) calendar days after contract award.
Contract Details & Timeline
- Contract Type: Firm-Fixed Price (FFP)
- Set-Aside: 100% Total Small Business Set-Aside (NAICS 238290, size standard $22,000,000)
- Place of Performance: Robins Air Force Base, Warner Robins, GA 31098
- Quotes Due: February 24, 2026, 01:00 PM EST
- Delivery/Installation: First lift within 12 weeks after drawing approval; remaining two lifts within 4 weeks after the first is installed.
- Vendor Questions: No longer accepted after COB February 20, 2026.
Submission & Evaluation
Quotes must be submitted via email to Contract Specialist Joshua Belzince (joshua.belzince@us.af.mil) and Contracting Officer Joshua Sharpe (joshua.sharpe.6@us.af.mil). Prospective vendors must provide documentation demonstrating adequate financial resources, including a narrative statement and substantiating documents. Evaluation will be based on the lowest price from a responsible offeror whose proposal conforms to the solicitation, including a financial capability review.