LOLO NATIONAL FOREST - Ninemile Water & Wastewater and St. Regis Wastewater Improvements

SOL #: 1240LU26Q0010Combined Synopsis/Solicitation

Overview

Buyer

Agriculture
Forest Service
LOLO NATIONAL FOREST
MISSOULA, MT, 59804, United States

Place of Performance

MT

NAICS

Water and Sewer Line and Related Structures Construction (237110)

PSC

Repair Or Alteration Of Water Supply Facilities (Z2NE)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Jan 27, 2026
2
Last Updated
Mar 5, 2026
3
Submission Deadline
Feb 27, 2026, 7:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Lolo National Forest is soliciting quotes for Ninemile Water & Wastewater and St. Regis Wastewater Improvements. This 100% Small Business Set-Aside opportunity, issued as a Request for Quotation (RFQ), seeks contractors for critical infrastructure upgrades. Quotes are due by February 27, 2026, at 12:00 PM Mountain Time.

Scope of Work

This project involves the replacement of the water distribution system and wastewater collection system at the Ninemile Ranger Station. Additionally, it includes the replacement of the wastewater collection system at the St. Regis Work Center. One potential option item is also included. It is critical to note that the St. Regis water system is NOT included in this contract and will be advertised separately. Detailed technical specifications, construction plans, and a schedule of items are provided in attachments for both Ninemile and St. Regis locations.

Contract Details

  • Contract Type: Request for Quotation (RFQ), anticipated Firm Fixed Price.
  • NAICS Code: 237110 (Water and Sewer Line and Related Structures Construction) with a size standard of $45.0 Million.
  • Set-Aside: 100% Small Business Set-Aside.
  • Bond Requirements:
    • Bid Bond/Offer Guarantee: 20% required if the quote exceeds $150,000.
    • Performance & Payment Bonds: Both required at 100% of the original contract price if the value exceeds $150,000, due 10 days after award. For contracts between $35,000 and $150,000, only payment protections (irrevocable letter of credit or payment bond) are required, due within 10 days of award.

Submission & Evaluation

  • Quote Due Date: February 27, 2026, 12:00 PM Mountain Time.
  • Submission: Quotes must be sent via email to Alisha Knaub at alisha.knaub@usda.gov.
  • Evaluation: Quotes will be evaluated using a comparative methodology, focusing on best value to the Government. Factors include Experience (demonstrated relevant experience in scope, size, and complexity), Past Performance (narrative of five relevant contracts within the last five years), and Price (considering base and option items, quantity discounts, and prompt payment discounts). This is not a Lowest Price Technically Acceptable (LPTA) evaluation.

Key Dates & Contacts

  • Response Date: February 27, 2026.
  • Published Date: February 9, 2026 (Amendment 001).
  • Primary Contact: Alisha Knaub, email: alisha.knaub@usda.gov, phone: (406) 438-2981.

Additional Notes

This is a combined synopsis/solicitation; no separate written solicitation will be issued. Amendment 001, posted on February 9, 2026, adds a formal site visit for the Ninemile project on February 18, 2026, at 9:00 AM at the Ninemile Ranger District (20325 Remount Road, Huson, MT). The point of contact for the site visit is Catina Mclean at 406-499-4842. No formal site visit is planned for St. Regis; contractors may view this site independently. Prevailing wage rates for Mineral and Missoula Counties, Montana, apply and are detailed in Attachments 7 and 8.

People

Points of Contact

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 6
Combined Synopsis/Solicitation
Posted: Mar 5, 2026
View
Version 5
Combined Synopsis/Solicitation
Posted: Feb 25, 2026
View
Version 4
Combined Synopsis/Solicitation
Posted: Feb 24, 2026
View
Version 3
Combined Synopsis/Solicitation
Posted: Feb 18, 2026
View
Version 2Viewing
Combined Synopsis/Solicitation
Posted: Feb 9, 2026
Version 1
Combined Synopsis/Solicitation
Posted: Jan 27, 2026
View