1
Posted
Apr 23, 2026
2
Last Updated
May 13, 2026
3
Submission Deadline
May 22, 2026, 1:30 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The U.S. Department of Agriculture (USDA) is soliciting quotations for Office Renovations at its Agriculture Marketing Service Cotton Classing Office in Corpus Christi, TX. This Total Small Business Set-Aside opportunity involves converting storage space into offices, upgrading the reception area, general flooring improvements, and adding limited electrical/telecom infrastructure. Quotes are due by May 22, 2026, at 8:30 AM CT.

Scope of Work

The contractor will provide all labor, materials, equipment, and supervision for renovations, including:

  • Front Office – Storage Area Conversion to Office: Repairing walls, repainting, recarpeting, modifying an existing door, and adding electrical/telecom receptacles.
  • Front Office – Reception Area: Removing the existing counter, fabricating and installing a new counter, recarpeting, and extending a wall with a new door.
  • General Storage Room – Conversion to Assistant AD Office: Removing shelving, repairing walls, repainting, recarpeting, modifying the existing door, and adding electrical/telecom receptacles.

All work must comply with federal, state, and local building codes and USDA standards. Finish selections and device locations require USDA approval. The project scope has been modified by amendments to remove specific hallways/breakroom flooring and a general office sliding door.

Contract Details

  • Contract Type: Combined Synopsis/Solicitation (Request for Quotations - RFQ)
  • Anticipated Award: Standard Form 1442
  • Period of Performance: Work must be completed within 60 calendar days from the Government’s Notice to Proceed (NTP).
  • Estimated Magnitude: $25,000 - $100,000.
  • Bonds: A payment bond is required within 10 days of award; a bid bond is not required.
  • Wage Rates: Bidders must adhere to Federal Construction Wage Rates for Nueces County, TX (TX20260288).

Submission & Evaluation

  • Submission Deadline: May 22, 2026, at 8:30 AM CT (updated by Amendment 0001).
  • Submission Method: Email to james.g.roloff@usda.gov.
  • Submission Package: Must include the quote page, demonstration of relevant experience, and past performance information.
  • Evaluation Criteria: Award will be made to the lowest price, technically acceptable offer. Only the lowest-priced quote will be evaluated for technical acceptability initially.

Key Amendments & Clarifications

  • Amendment 0003 (May 7, 2026): Removed hallways and breakroom flooring from the project scope.
  • Amendment 0002 (May 6, 2026): Removed the general office sliding door from the project scope.
  • Amendment 0001 (April 27, 2026): Changed the quote submission time to 8:30 AM CT on May 22, 2026.
  • RFIs: A site visit was highly recommended, and a floor plan was provided. The contractor is responsible for supplying and installing all telecom cabling.

Contact Information

People

Points of Contact

Files

Files

Download
Download
Download
Download
Download
Download
Download

Versions

Version 8
Combined Synopsis/Solicitation
Posted: May 13, 2026
View
Version 7Viewing
Combined Synopsis/Solicitation
Posted: May 7, 2026
Version 6
Combined Synopsis/Solicitation
Posted: May 6, 2026
View
Version 5
Combined Synopsis/Solicitation
Posted: May 5, 2026
View
Version 4
Combined Synopsis/Solicitation
Posted: Apr 29, 2026
View
Version 3
Combined Synopsis/Solicitation
Posted: Apr 27, 2026
View
Version 2
Combined Synopsis/Solicitation
Posted: Apr 27, 2026
View
Version 1
Combined Synopsis/Solicitation
Posted: Apr 23, 2026
View