B149 Chiller Replacement at Pease ANGB

SOL #: W50S8A26QA010Combined Synopsis/Solicitation

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Army
W7NN USPFO ACTIVITY NHANG 157
PORTSMOUTH, NH, 03801-2886, United States

Place of Performance

NH

NAICS

Plumbing (238220)

PSC

Air Conditioning Equipment (4120)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
May 6, 2026
2
Last Updated
Jun 11, 2026
3
Submission Deadline
Jun 5, 2026, 8:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The NH Air National Guard is soliciting quotes for the B149 Chiller Replacement project at Pease Air National Guard Base (ANGB). This is a Total Small Business Set-Aside for a Firm-Fixed Price (FFP) contract to remove an existing chiller and install a new, fully operational system. Quotes are due by June 5, 2026, at 04:00 PM Eastern Time.

Scope of Work

The project requires the complete removal and disposal of the existing chiller and the provision and installation of a new, fully operational chiller system at Building 149. Key tasks include:

  • Furnishing all labor, materials, and equipment.
  • Removing and disposing of the existing air-cooled chiller, buffer tank, and associated piping.
  • Installing a new, like-for-like, 25-ton modular air-cooled chiller (10-ton and 15-ton modules) and a 460-gallon buffer tank.
  • Ensuring compatibility with the existing Schneider Electric base-wide control system.
  • Providing new electrical wiring, disconnects, and circuit breakers.
  • Installing a 30% glycol solution in the chilled water loop.
  • Replacing and reprogramming all HVAC controllers with Bacnet compliant, Schneider Electric IP controllers.
  • Adding new graphics to the existing Schneider Electric central Building Management server.

Contract & Timeline

  • Solicitation Number: W50S8A26QA010
  • Type: Request for Quote (RFQ), Firm-Fixed Price (FFP)
  • NAICS Code: 238220 Plumbing, Heating, and Air-Conditioning Contractors (Small Business Size Standard: $19,000,000)
  • Set-Aside: 100% Total Small Business
  • Place of Performance: 302 Newmarket Street, Newington, NH 03801 (Pease ANGB)
  • Period of Performance: Work to be completed within 135 calendar days of contract award.
  • Published Date: May 14, 2026
  • Quote Due Date: June 5, 2026, 04:00 PM ET
  • Quotes Validity: 60 days

Evaluation

Quotes will be evaluated in accordance with FAR 52.212-2, as detailed in the "Provisions and Clauses" document. Bidders should review these documents for specific evaluation factors, which typically include price, technical capability, and past performance.

Additional Notes

  • Funding: Award is contingent upon the availability of adequate funds (see FAR 52.232-18).
  • Site Visit: A site visit will be held on Thursday, May 21, 2026, at 1:00 PM EST. Interested parties must submit attendee names and contact information by 4:00 PM on May 19, 2026, to Casey Pridham and Matthew Lapointe.
  • Questions: All technical or contractual questions must be submitted in writing via email to Casey Pridham (casey.a.pridham.mil@army.mil) and Matthew Lapointe (matthew.r.lapointe.civ@army.mil) by 12:00 noon EST on May 26, 2026. Telephone inquiries will not be accepted. The RFI period was extended to accommodate questions resulting from the site visit.
  • SAM Registration: Active registration in the System for Award Management (SAM) at www.sam.gov is required for award consideration.

People

Points of Contact

Files

Files

Download
Download

Versions

Version 8
Combined Synopsis/Solicitation
Posted: Jun 11, 2026
View
Version 7
Combined Synopsis/Solicitation
Posted: Jun 9, 2026
View
Version 6
Combined Synopsis/Solicitation
Posted: Jun 7, 2026
View
Version 5
Combined Synopsis/Solicitation
Posted: Jun 4, 2026
View
Version 4
Combined Synopsis/Solicitation
Posted: May 21, 2026
View
Version 3
Combined Synopsis/Solicitation
Posted: May 21, 2026
View
Version 2Viewing
Combined Synopsis/Solicitation
Posted: May 14, 2026
Version 1
Combined Synopsis/Solicitation
Posted: May 6, 2026
View