TINKER AFB MAC BOA WWYK150083 - Repair Transformer Vault 6, B9001
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Air Force is soliciting proposals for WWYK150083 - Repair Transformer Vault 6, B9001 at Tinker Air Force Base, Oklahoma. This opportunity is exclusively for Tinker AFB MAC BOA Holders. The project involves critical electrical infrastructure repair and replacement. Proposals are due March 13, 2026, at 2:00 PM CST.
Scope of Work
This project entails the repair by replacement of two gas-filled 2000KVA transformers, associated 480V switch gear (#6C and #6D), all 15KV switches, and the original 3000A tie bus within Transformer Vault 6, Building 9001. These components have exceeded their rated life expectancy. Additional work includes repairing interior lighting, adding visual fire alarm notification devices to meet ABA requirements, and repairing the vault's exterior. The scope also covers necessary logistical, architectural, and structural work to ensure a complete system.
Contract Details
- Type: Negotiated (RFP)
- Solicitation Number: FA813726R0008
- Estimated Magnitude: Between $1,000,000 and $5,000,000 (IAW FAR 36.204)
- Set-Aside: Total Small Business Set-Aside (FAR 19.5)
- Place of Performance: Tinker AFB, B9001, S Coffeyville, OK
- Performance Period: 10 calendar days to commence work after Notice to Proceed (NTP), with 271 calendar days to complete the entire work.
- Liquidated Damages: $277.75 per calendar day for delays.
Key Requirements & Clarifications
- Eligibility: Mandatory for Tinker AFB MAC BOA Holders ONLY. A mandatory initial site visit was held on February 5, 2026; attendance was required for eligibility to propose. The site visit sign-in sheet is available.
- Environmental: The project does not require the use or delivery of Class 1 Ozone Depleting Substances (ODS). Bidders should consider environmentally preferable purchasing as per the Recovered Materials Determination Form.
- Technical: Existing transformers are gas-filled (no PCB testing required). Custom busway adapters are intended. Project will follow 2025 Tinker AFB electrical standards. Demo work will be phased to minimize production impact, maintaining power continuity. Pre-bid RFI responses have been attached, clarifying several technical points.
- Labor: Prevailing wage rates and fringe benefits for Oklahoma County, Oklahoma, apply as per the General Decision Number.
- Documentation: A comprehensive Submittal Register outlines all required documentation throughout the project lifecycle. Project drawings, including a Sheet Index, Vicinity Map, and Building Key Plan, are available.
Submission & Evaluation
- Proposal Due Date: March 13, 2026, at 2:00 PM CST (1400CST).
- Submission: Proposals must be submitted in original and 1 copy. Offers must be valid for at least 120 calendar days.
- Evaluation: Criteria will be detailed in Section M of the solicitation. Performance and Payment Bonds are required.
- Contact: Primary contact is Sara Hinds (sara.hinds.2@us.af.mil).