TINKER AFB MAC BOA WWYK150083 - Repair Transformer Vault 6, B9001
SOL #: FA813726R0008Pre-Solicitation
Overview
Buyer
DEPT OF DEFENSE
Dept Of The Air Force
FA8137 AFSC PZIOC
TINKER AFB, OK, 73145-9125, United States
Place of Performance
S Coffeyville, OK
NAICS
Commercial and Institutional Building Construction (236220)
PSC
Repair Or Alteration Of Restoration Of Real Property (Public Or Private) (Z2QA)
Set Aside
Total Small Business Set-Aside (FAR 19.5) (SBA)
Original Source
Timeline
1
Posted
Jan 21, 2026
2
Last Updated
Mar 13, 2026
3
Response Deadline
Mar 25, 2026, 9:00 PM
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Air Force is soliciting proposals for WWYK150083 - Repair Transformer Vault 6, B9001 at Tinker Air Force Base, Oklahoma. This project involves the repair and replacement of critical electrical infrastructure. This opportunity is a Total Small Business Set-Aside and is restricted to Tinker AFB MAC BOA Holders Only. Proposals are due March 25, 2026.
Scope of Work
The project entails furnishing all materials, labor, and equipment to:
- Repair and replace two gas-filled 2000KVA transformers.
- Replace associated 480V switch gear (labeled #6C and #6D).
- Replace all 15KV switches and the original 3000A tie bus.
- Repair interior lighting and add visual fire alarm notification devices to meet ABA requirements.
- Repair the vault's exterior at Building 9001.
- Perform necessary logistical, architectural, and structural work, including a site investigation.
Key Requirements & Clarifications
- Mandatory Site Visit: Attendance at the initial site visit (held February 5, 2026) was mandatory to be eligible to propose.
- Environmental Compliance: The project does not require the use or delivery of Class 1 Ozone Depleting Substances (ODS).
- Pre-bid RFIs: Responses to pre-bid RFIs clarify details such as transformer type (gas-filled, no PCB testing), busway transition, existing busway (ITE XL-X), DPM meters, and phasing requirements to minimize production impact. The project will follow 2025 Tinker AFB electrical standards.
- Wage Determination: Bidders must comply with prevailing wage rates and fringe benefits for Oklahoma County, Oklahoma.
- Submittals: A comprehensive submittal register outlines all required documentation throughout the project lifecycle.
- Recovered Materials: The procurement process considers environmentally preferable purchasing, including recovered materials.
Contract Details & Timeline
- Contract Type: Negotiated (RFP)
- Set-Aside: Total Small Business Set-Aside (FAR 19.5) - Restricted to Tinker AFB MAC BOA Holders Only.
- Magnitude: Between $1,000,000 and $5,000,000.
- Performance Period: 10 calendar days to commence work after Notice to Proceed (NTP), with 271 calendar days for completion.
- Liquidated Damages: $277.75 per calendar day of delay.
- Proposal Due Date: March 25, 2026, at 1600 CST.
- Contacts: Sara Hinds (sara.hinds.2@us.af.mil) and Megan Donaghe (megan.donaghe@us.af.mil).