Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The USDA-APHIS-Wildlife Services is soliciting quotes for the construction of a new kennel building in Millville, UT. This opportunity is a Total Small Business Set-Aside and seeks a pre-engineered metal building of approximately 3,400 SF. Quotes are due by April 29, 2026, at 11 a.m. MT.
Scope of Work
The project involves constructing a new pre-engineered metal kennel building, approximately 3,400 square feet, based on final design documents by Cushing Terrell. The structure will include four sections: kennel areas A & B, a mud room, and a mechanical room. This facility supports the Predator Research Facility's mission to generate ecological information for carnivore management. Work is expected to commence within 10 calendar days after Notice to Proceed (NTP) and be completed within 365 days after NTP.
Contract & Timeline
- Contract Type: Combined Synopsis/Solicitation (Request for Quotations - RFQ)
- Estimated Magnitude: Between $1M and $5M
- Set-Aside: Total Small Business Set-Aside (FAR 19.5)
- Quote Submission Deadline: April 29, 2026, 11 a.m. MT
- Questions Deadline: April 24, 2026, 12 p.m. CT
- Published Date: April 23, 2026
Submission & Evaluation
Quotes must be submitted to james.g.roloff@usda.gov and include the RFQ page, a detailed pricing breakdown, demonstration of relevant experience, and past performance information. Evaluation will be based on the highest technically rated with a fair and reasonable price, with no tradeoffs between price and non-price factors. Evaluation factors include Price, Technical Capability (experience with pre-engineered metal buildings, technical approach, work sequencing, project management, quality control, and safety), and Past Performance.
Key Documents & Notes
- Amendment 1 updated the set-aside from SDVOSB to Total Small Business.
- Construction Documents: Detailed architectural, civil, structural, mechanical, plumbing, and electrical drawings (Attachment 4) and a comprehensive Project Manual (Attachment 3) are provided.
- Geotechnical Report: Outlines subsurface soil and groundwater conditions, providing recommendations for foundation, earthwork, and pavement design.
- Wage Rates: Attachment 2 specifies Federal Construction Wage Rates for Cache County, UT.
- RFIs: Confirmed roof panel type is PBU and roof/soffit gauge is 24 gauge.
- Site Visit: An attendance sheet from a previous site visit is available, potentially listing interested parties.
- Contact: Jim Roloff, james.g.roloff@usda.gov, 612-590-7603.