WA NP MORA 11(1), Fryingpan Creek Bridge
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Federal Highway Administration (FHWA), Western Federal Lands Division, is soliciting bids for the WA NP MORA 11(1), Fryingpan Creek Bridge Replacement Project within Mount Rainier National Park, Pierce County, WA. This project involves the construction of a new bridge and associated infrastructure. Bids are due by July 1, 2026.
Scope of Work
This project entails the replacement of the Fryingpan Creek Bridge with a new single span, 218.5-foot long steel plate girder bridge featuring a cast-in-place concrete deck, founded on deep foundation drilled shafts. Key deliverables include:
- Demolition of the existing steel arch girder bridge.
- Roadway realignment and parking lot construction.
- Minor pipe culvert replacement and stone masonry work (matching historic character).
- Earthwork, aggregate, asphalt, and concrete paving elements.
- Slope reinforcement, retaining walls (using hot-dipped galvanized steel mesh reinforcement only).
- Traffic control measures, log deflectors, and root wads.
- Work is to be performed under two separate bid schedules (A and B), requiring compliance with Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14, and U.S. Customary units.
Contract & Timeline
- Contract Type: Firm Fixed-Price with Economic Price Adjustment.
- Estimated Price Range: $15,000,000 to $25,000,000.
- Period of Performance: Commencement within 10 calendar days after Notice to Proceed (NTP), with completion not later than September 28, 2029, for both schedules. The NTP date is revised to August 25, 2026.
- Set-Aside: This is an unrestricted solicitation. Large businesses are required to submit an acceptable subcontracting plan prior to contract award.
- Response Due: July 1, 2026, at 21:00:00Z.
- Published Date: June 12, 2026.
Submission & Evaluation
Bids must be submitted as a printed copy; electronic bids are not authorized. A bid bond is required, along with a completed "Authority to Sign" document and Representations & Certifications. The evaluation includes a 10% price factor applied to an apparent low bid from a large business if a HUBZone small business also bids.
Key Clarifications & Notes
- The project advertisement was anticipated in Spring 2026 (April/May).
- Stevens Canyon Road access for avalanche chute harvesting is available 1-2 weeks prior to the public opening (May 22nd).
- Road closures are limited to 6 hours per calendar day, daytime only, with no night work or consecutive closures.
- Drilled shaft construction expects boulders and difficult drilling conditions; no separate pay item will be provided for these.
- Temporary work bridges may remain for up to three consecutive construction seasons, but stream diversions must be removed at the end of each season.
- Bidders must acknowledge all amendments (A001, A002, A003). Amendment A002 extended the bid due date, and A003 replaced the bid schedule and updated various documents.
- General questions can be directed to Contracts G. Office at wfl.contracts@dot.gov or 360-619-7520. Technical questions to wfl.plans-spec@dot.gov.